Addition Day 30 - Friday was officially day 29

The plumber did come on Friday and put the piping in that was needed to be installed for the roof so that the metal roofing can be installed hopefully within the next few days now.  I didn't post any pictures of that. So here is a few pictures of the roof with the pipes.



















Saturday the contractor put a lot of materials including the kitchen cabinets in to the addition for the job while it was dry and a good opportunity to get things in there.  Today some of the insulation was installed. 



















And the window that we salvaged from the dining room wall that is going to have mom's bedroom door added, was installed by the contractor just now.  It will be just on the right side once her bedroom door is opened and you walk in. There are no lights inside yet so it it was hard to take pictures inside which I tried to make as light as I could.



SEE THE VIKING ARMOR PAPER? THAT IS WHERE THE DOOR IS GOING